How much reserve stone does a hotel need, and where is it kept?
In brief. The question is almost always asked late, once the hotel is open and a top has broken. Reserve stone is not a percentage added to the order: it is a particular piece, taken from the right material at the right moment and kept so that in a few years' time it is still sound and, above all, still identifiable. Take away any one of those three and the reserve exists without being of use.
Why «the same marble» in three years is not the same marble
A natural stone has a commercial name, not a recipe. Slabs cut from the same block resemble one another because they are successive bands of the same body of stone: they read in sequence, one after another. Slabs of the same name taken from different blocks can differ in ground, veining and tone, and the difference shows the moment the two pieces stand in the same room.
From which follows the first rule, and it is a rule about timing rather than quantity: a reserve bought afterwards is not a reserve, it is another stone. The only one that works is the one set aside while the block was still available, which means at the beginning, together with the material for the supply: it is why on a project the stone is all committed at once, as we write in «who supplies the stone tops of a hotel» (/en/guides/who-supplies-stone-tops-for-hotels). How the material is approved before production is in «how to pick a marble slab» (/en/guides/how-to-pick-a-marble-slab).
Is a slab set aside, or a finished piece?
They are two different reserves answering two different problems.
The finished piece — cut to the dimensions of that top, with its cutouts and its edge profile — answers the case that actually occurs: a top breaks and the room has to reopen. It is the reserve that saves days: there is nothing to fabricate, it is swapped.
The uncut slab answers everything else: a piece other than the one foreseen, an area rethought, work done some years later. It keeps the options open, at the cost of fabrication time at the moment it is needed.
On a project with many rooms the choice is not between the two but how many finished pieces and how much slab. And the criterion is not a percentage: it is exposure.
Which pieces are worth it, and which are not
The pieces that break and get marked are always the same ones.
First, tops with a cutout. The cutout is where the slab is already weakened, and a knock that leaves no trace elsewhere opens a crack there: we write about it in «cracks at the cutouts» (/en/guides/cracks-at-sink-and-hob-cutouts).
Second, the pieces that live among people: the runs of the bar counter, the restaurant table tops, the reception desk. They get marked through use, not through any defect.
Third, strongly patterned pieces, where a replacement taken from another block would show. On a stone with a uniform ground the problem barely exists; on a heavily veined stone the reserve is worth more than it costs.
It is generally not worth it for what can be put right in place: a chip on an edge is dealt with where it is, as in «repairing a chipped top» (/en/guides/repair-chipped-marble-top). Nor for small pieces that can be got out of an offcut: whose the offcuts are is a matter to settle in writing (/en/guides/leftover-stone-who-owns-it).
One observation runs against intuition: a reserve pays off most where the pieces are many and identical. Eighty identical vanity tops make one spare top a small cost per piece, and the chance that it will eventually be needed is high.
Where it is kept, and how a reserve is spoiled
A reserve is lost more often in storage than on site, for two mundane reasons.
The first is how it stands. Slabs are kept upright, leaning at a slight angle against an A-frame, separated by battens and with their edges protected. Stacked flat on the floor one on top of another they chip along the edges, and the bottom one becomes the slab nobody will use. They belong indoors, dry, clear of the floor, and not wrapped in plastic, which holds the moisture in. Not in a circulation corridor either: every move is a risk, and a slab does not move on its own — «how much does a stone top weigh» (/en/guides/how-much-does-a-stone-top-weigh).
The second is identification, and it does more damage than the first. A reserve slab with nothing written on it is, three years later, just a slab: nobody will be able to say whether it is the right one, which block it came from, what thickness it is or what finish it carries. It happens often: the reserve is there, it is sound, and it cannot be used because it cannot be identified.
What has to be written down for it to be of use years later
A reserve is as useful as its label. The entries needed are few, and they belong on the piece and, in copy, in the supply dossier: the name of the stone and the reference of the block or lot it was cut from; the thickness; the finish; what it was for, which top of which room type; the date and the name of whoever fabricated it.
Alongside, two things belong somewhere they will not be lost. The drawing of the pieces, because a replacement is remade to the dimensions and not to recollection. And a cut, numbered sample of the same material, which is the instrument by which the new stone will be judged to match: it is the same reference sample we write about in «defect or natural feature» (/en/guides/stone-defect-or-natural-feature).
Who keeps it: the hotel or the workshop?
The two arrangements have opposite drawbacks, and the choice belongs in writing.
Kept by the hotel, the reserve is at hand and nobody commits it by mistake to another job; but a hotel store is a place of passage, and in three years a slab standing in a plant room becomes an obstacle to be shifted — and a slab shifted badly is a slab chipped.
Kept by the workshop, it sits where stone is stored for a living and where there are people who know how to handle it; but for how long, and who it is to be asked for, have to be set down.
In both cases two points belong in writing: that the reserve belongs to whoever paid for it, and who releases it, to whom, and on what notice.
How we work
We buy the blocks directly at the quarry and cut the slabs in our own workshops, and on a project that changes two things. The first is that the material is committed at the outset, on the block, so the reserve is decided there, while there is still a choice to be made: the client sees the slab selection before production and says where the pieces are to be taken from. The second is that the drawing stays in house, so a piece is remade years later to the same dimensions.
The trimmings from the slabs become smaller pieces that go into our collections. Which is also the practical reason a reserve is better decided than improvised: stone, once cut, does not go back.
On tops we do not use resin to stiffen the stone: where the surface is large the correct answer is a support.
The route of a project supply is in the contract (/en/contract) section; the answers we give studios in writing are in «the questions studios ask us» (/en/studio-questions); the supply chain and the waste in «environment and materials» (/en/sustainability); the work in the collections (/en/collections); and the contact details (/en/#contatti) lead to the people who follow the fabrication.
How much reserve stone is kept, as a percentage?
It is not a percentage: it is a list of pieces. You start from the most exposed and the most repeated. A percentage of the total, on a supply made up of elements unlike one another, says nothing useful.
If no reserve was kept, what then?
You look for the closest material and decide where to put it, which is the part that matters. The practical rule is not to set a different piece among identical ones: if the difference shows, better to redo a whole area than to place two tones in the same room. Where the joints fall is in «a marble top without seams» (/en/guides/marble-top-without-seams).
Can a reserve piece be adapted to another size?
It can be reduced, not extended, and any work on an already finished piece has its limits: it is the same argument as for tops already installed, in «can a fitted stone worktop be modified» (/en/guides/modify-fitted-stone-worktop).
Ask for a quotation The tables collection
This page sets out assessment and selection criteria; it quotes no prices, no intervention times and no company case studies. The fabrication indications are those of good stoneworking practice and have to be checked against the actual case, because they depend on the stone, the dimensions and the supporting structure. No technical standard is cited, because requirements change with the intended use of the room.