The wall is not square: who straightens it, and who pays?

In short. Between a stone worktop and a wall that is out of square there is a gap that opens out from one end of the run to the other: it is not a fault in the cutting, it is the wall. Who pays almost always turns on a single act, the survey of the measurements on site, because whoever carries it out takes the wall as they found it. There are three routes, and two of them have to be chosen before the slab is cut.

Why does being out of square show on the worktop and not on the units?

Units are separate modules: each base is plumbed on its own, the millimetres are shared out between one carcase and the next, and whatever is left is covered by end panels and plinths. A stone worktop is a single rigid piece cut along a straight line: it has no slack to share out, so the error does not spread, it collects at one end. And the discrepancy grows with the length of the piece: the same angle that cannot be read over half a metre opens, on a long run, a gap that is visible from across the room.

Pushing the stone against the wall to close the gap is the thing not to do: stone does not deform, and forcing it makes it bear on a few points instead of along its whole side — the condition that cracks at the sink cutout come from.

Which act decides who pays?

The survey of the measurements on site. A stone worktop is not cut to the measurements on the drawing: it is cut to the ones taken on site, with the base units already fitted. That moment is the only one in which somebody looks at the real wall rather than the wall of the design, and it is therefore also the moment at which the wall changes hands. In practice there are three configurations.

Almost nobody writes down what follows: the question to ask before ordering is not «how much does it cost», it is who is coming to measure, and what do they sign. A survey is a document with a date on it, not a telephone call (see also who carries the top up and who fits it).

How far out of square is normal?

No plastered wall is square, and being out of square is not in itself a defect: it becomes one when it exceeds the tolerance agreed for that work. This page gives no figure, because the tolerance on walls belongs in the specification for the building work and not in the one for the furniture: asking it of the worktop maker is asking the wrong person. What can be settled is how to measure, and the reading that matters is not the angle, it is the gap: its width in millimetres, taken against the line of the base units at both ends of the run and written into the survey. «The wall is crooked» is not a reading; two measurements are.

The three routes, and the order they are chosen in

The choice depends above all on how close the cutting is: before the slab is bought all three are open, after the survey two remain, after the cut only one (how to pick a marble slab).

And if the worktop is already cut to the old wall?

It is the commonest case of all, and it always comes from the same sequence: the survey is done, then somebody skims, tiles or clads the wall, and the piece arrives when the wall is no longer the one that was measured. Cladding adds thickness, so the worktop does not become short: it becomes long, and it will not go in. Who pays is then settled on a matter of fact, namely who touched the wall after the survey. That is why the most useful line to put in an order is not about tolerances but about sequence: after the survey, no work on the walls without telling whoever measured them. It is free, and it closes off half the disputes in advance.

A piece already cut can be worked on, but it is not a neutral operation: water and dust on a finished piece, close to the holes and cutouts that are its most stressed points, and the remade edge has to be brought back to the finish of the rest.

Does anything change on a hotel contract?

The physics does not, the organisation does. Being out of square repeats itself bathroom by bathroom with different values, and a solution that is good for one room and bad for another, multiplied by the rooms, becomes a series of decisions to be taken on site. The mock-up room exists for this: to let the problem be seen once instead of fifty times. And surveying fifty bathrooms is not a site visit, it is an item of time in the programme, placed after the wall finishes and before the slabs are ordered. Whoever is coordinating has one thing to fix, and it is worth more than any tolerance: the date after which the walls are not touched again (stone tops for hotels).

What the order and the specification should say

How we work

A worktop is cut once only, and that governs the order of things: first the measurement taken where the worktop will go, then the drawing, then the slab. When the sequence is reversed, being out of square is not discovered: it is suffered. In our quarry the blocks are cut to the client's instructions, and when we do not have a stone as a block we buy the slabs from importers we trust. For a contract supply the route is the Contract section; the contacts lead to the people who follow the work, and the tables show the work on a single piece.

Frequently asked questions

Is a wall out of square the contractor's defect?

It depends on the tolerance agreed for that building work, which belongs in the specification for the works and not in the one for the furniture. With no figure written down it stays one opinion against another; with a figure written down it becomes a check.

Can the wall be skimmed after the worktop has been cut?

It can, but it does not help: skimming adds thickness, so a piece cut to the old wall becomes too long rather than too short. If the wall needs correcting, it needs correcting before the survey.

Who ought to notice that a wall is out of square?

Whoever carries out the survey: they are the only one who goes there with an instrument. But whoever places the order can ask that the survey record the measured value, which is the difference between noticing it and being able to prove it.

Ask for a quotation The tables collection

This page describes assessment and selection criteria and does not replace a design. It quotes no prices, no response times, no tolerance values and no company case histories, and it cites no technical standards: tolerances on the squareness of walls depend on the specification for the building work and have to be agreed between the parties. The guidance on surveying, scribing and joints is that of good practice and has to be verified case by case.