Should the worktop come from the stone fabricator or from the kitchen supplier?

In short. You can buy it separately, and it is normal for it to cost a great deal less. What changes is not the stone: it is that with two suppliers nobody is answerable for the finished result any more. Three jobs that sit inside the supply when there is one supplier are left without an owner when there are two: re-levelling the units under the weight of the worktop, seating the sink and the hob, and taking the measurements on site.

Why is the kitchen supplier's quotation so much higher?

Almost always it has nothing to do with the quality of the stone and everything to do with the chain. A reseller generally adds between 35 and 50 per cent to the maker's price, and a maker who imports the stone directly saves a further 20 per cent or so on the material: two margins that add up and that in stone weigh more than the finish, the edge or even the thickness — on how the price is built up there is the page on how much a bespoke marble table costs. So when a local fabricator quotes half, as a rule nothing has been taken away from the stone: a step has been taken out of the chain.

Why the worktop is ordered after the kitchen has been fitted

A stone worktop is the last piece to enter a kitchen, and not out of habit. Design dimensions almost never hold on a real wall: walls are not square, and base units line up with what they find. The piece is not cut to the drawing; it is cut to a survey taken once the units are fitted, in position and levelled.

That is the sequence the users describe in the discussion this page comes from: first the kitchen is fitted, then the dimensions are taken to the millimetre together with any out-of-square, then the worktop is ordered. With a single supplier those are two visits by the same team; with two they become two separate jobs, and between them there is an interval in which the kitchen is fitted and has no worktop. In the discussion it runs from a few days to a few weeks: a figure to have written down.

Who re-levels the units under the weight of the worktop?

This is the question put by a kitchen retailer inside the discussion, and it is the most useful contribution in the whole thread. Setting a quartz or stone worktop, he writes, is not only a matter of measurement: the weight of the material may call for the levelling of the unit to be checked again and corrected, and once the worktop is down the hob and the sink are seated into it. Whether the fabricator is willing to do all of that is his question.

A second retailer answers from the other side, and says it plainly: he would not send his own fitters back to re-level a kitchen and position appliances he had not supplied himself. Neither of them is in the wrong. Each is answerable for what he sold, and the final levelling is in neither contract.

This is not fussiness: a square metre of stone 3 cm thick weighs around 81 kg — how much a stone top weighs does the arithmetic in full. Under that load a unit that was level may no longer be, and stone does not flex: it breaks.

Who seats the sink and the hob?

The cutouts are the most delicate part of the piece, and the point where the two supplies meet. An undermount sink has to be carried by something that is not the worktop: what actually holds it is a design decision. And the cutouts are the places a stone worktop cracks from, because the section is reduced there.

With a single supplier these operations stay in the hands that cut the piece. With two, one makes the cutout and the other seats the appliance: what happens between those two operations has to be assigned beforehand, in writing, because afterwards it cannot be assigned at all.

Two different surveys, and they are always confused

In stone there are two surveys, taken at different moments and for different reasons, both going by the same word.

One rule follows, and it always holds: whoever cuts must measure. If the fabricator cuts to dimensions taken by somebody else — the retailer's drawing, the designer, you — then in the event of an error nobody is answerable: he executed a wrong dimension correctly, and the other party supplied a dimension he never checked on site. The drawing serves as a reference for the position of the sink and the hob, not as a dimension to be executed. It is not an Italian problem only: in an English-language discussion a client lists, on a newly fitted granite worktop, a hob cutout out of square, a wrong sink cutout and a tap shifted to the window sill, and a fabricating business replying in the thread puts those defects down to a badly executed field measure.

What to put in writing before splitting the supply

Seven lines, to be asked of both suppliers before signing.

If on any one of those lines a supplier answers «we'll see on site», that line is still unassigned, and the site where it will be seen is your kitchen.

When splitting is worth it, and when it is not

It is worth it when the kitchen is a straight run, at a standard depth, in one or two pieces, with no undermount sink; when the fabricator puts survey, delivery, cutouts and fitting in writing; and when the kitchen supplier knows before he takes his measurements.

It is not worth it with an island or a peninsula, with walls out of square, with an undermounted sink, when the figure of the stone has to carry on from one piece to the next — how long a worktop can be without seams shows where the limit falls — and when the commercial name is not enough to identify the stone, as the page on quartzite and marble shows.

And it is never worth it when there is a date. In a hotel contract the value that weighs most is time: a supply split between two companies has two calendars, the second starts when the first finishes, and a bedroom is not handed over half finished. The route of a contract is in the Contract section, and who supplies the stone worktops of a hotel is a different question, with another answer.

How we work

Stoneform makes tables, worktops and works in marble, onyx and natural stone. We buy the blocks directly at the quarry and cut the slabs ourselves, in our own factory: which is why the reseller's step, with its mark-up, does not exist here. We quote a piece on the drawing and on the slab it will be cut from, with the items separated as set out above.

On contract work the survey on site and the fitting are part of the job and we carry them out ourselves: the Contract page shows some operations photographed during production, the table collections show how we work when there is only one piece, and the contacts reach the people who follow the work. A 240 cm marble table costs in the region of 3,800 euro: an order of magnitude rather than a price list, because the price depends on dimensions and finish.

Frequently asked questions

Do I have to tell the kitchen supplier that the worktop is coming from elsewhere?

Yes, and before he takes his measurements. It is not courtesy: his sequence changes, and he needs to know the worktop is not his in order to decide whether his fitters will be coming back a second time. If he finds out once the kitchen is fitted, that visit is not in his contract.

If the fabricator does not re-level the units, who does?

Nobody, unless it has been agreed: it is the most frequent gap in a split supply. It has to be assigned in writing to one of the two, with its cost, before ordering.

Is the retailer's kitchen drawing enough for the fabricator?

As a reference, yes; as a dimension to be executed, no. The dimensions the piece is cut to have to be taken on site by whoever cuts it: it is the only way that, if the piece arrives wrong, somebody is answerable.

Ask for a quotation The tables collection

This page describes how a supply is organised and the criteria for splitting it: it quotes no list prices and no response times. The fitting sequence, the question about re-levelling the units under the weight of the worktop and the answer about sending fitters back are reported as contributions to a public discussion among users and trade members on a furnishing forum, read in full, and they are the opinions of the people who wrote them rather than practice we assert as general. The reference to the survey on site as the origin of a worktop's defects is reported in the same way, from an English-language discussion. The percentages on the intermediate commercial steps and the indicative price of the 240 cm table are orders of magnitude, not price lists. The standards on the weight of stone, on liability in transport and on units of measurement are cited in the linked pages, where they appear with their references. Assessing an individual case is for whoever can see the place and the dimensions.