How long does a bespoke stone top take?
In brief. There is no number that holds for everyone, and anyone who gives one over the telephone is talking about a different piece. The lead time of a bespoke stone top is not counted from the order but from two moments the order does not control: when the slab is actually committed, and when the template can be taken. Between the two lies a chain of operations carried out one after another. Anyone who wants a reliable date does not ask for it while negotiating: they tie it to the template and write it into the order.
The clock does not start at the order
A stone top is not an item off a shelf: it is a piece taken from one particular slab and cut to measurements recorded in place. Which is why the order — the moment the client feels things have been set in motion — sets almost nothing in motion. Two clocks start, and neither is looked at while negotiating.
The first is the material's. Natural stone has a trade name, not a recipe: two slabs with the same name can differ, and availability is a matter of the warehouse, not of the catalogue. Until you know which slab the piece comes out of nothing is certain, and choosing one is not a detail to be dealt with last: see the guide on how to pick a marble slab.
The second is the site's. A piece that meets walls and units is cut to measurements taken in place, not to the drawings: walls are rarely square, and the drawing does not say so — the guide on a wall out of square. The template can be taken only once the units are installed and the walls finished, a point that does not depend on the stone supplier: what has to be there on the day is the guide on template day.
The steps that do not overlap
Inside the workshop, time is a queue and not a heap: each step takes the previous one's result as input.
- finding the right slab and committing it — the one thing that can be done ahead of everything else, and the one almost everyone does last;
- the template, on site, with the units installed;
- the approved shop drawing: where the seams fall, which edge profile, how the sink housing and the cutouts are made;
- cutting from the slab, the point of no return: from then on the slab is that piece;
- the edges and the cutouts, then the surface finish;
- the bonded assemblies — upstands, built-up edges, workshop joints — whose curing time heat does not shorten;
- packing, transport and installation, with all that access and unloading involve: the guide on delivery and fitting.
The practical consequence is one: no time is gained by pressing at the end. It is gained at the start, by bringing forward the two things at the head of the queue — the slab and the template.
What makes a date slip, nearly always
The causes are few and they repeat:
- the slab is not there any more. A material seen months earlier may be gone, or read differently. Looking for the stone after the installation date has been fixed is the commonest way of losing weeks with nobody at fault;
- the site is not ready on template day. A postponed template moves the whole queue behind it, and the workshop slot that had been held goes to another job;
- something is changed after the template. Changing the sink, the hob, the tap or the thickness means redoing the shop drawing and, if the cutting is done, remaking the piece. The drawing needs the appliances' technical sheets, not their trade names;
- a piece breaks. A top that breaks in the workshop, in transit or at installation is not repaired the same day: it is remade, from the same slab if that slab is still there. It is the technical reason a project is planned with attic stock;
- a decision left open. Where a seam falls and which edge profile to use look like aesthetic choices to be made at leisure: they are the two lines that hold up the shop drawing, and until they arrive the piece is not cut.
What actually shortens the time
Four things, and none of them costs money:
- deciding the material early and committing the slab, well before the site is ready: stone in a store does not deteriorate, a decision left open does;
- freezing the appliances before the template and handing over their sheets: the item that causes the most remakes;
- turning up to the template with the room genuinely finished, not nearly: a template taken on units that are not levelled has to be taken again;
- accepting one more joint where it makes sense: a single very long piece is slower to find, to work and to carry in than two well matched.
What shortens nothing is asking for priority: the queue is not a line at a counter but a chain of operations, and a piece pushed ahead of the others skips a step that has to be done again.
On a hotel project time does not add up, it multiplies
In a hotel the same stone has to repeat across dozens of rooms, and that changes the problem: the slabs have to come from the same body of material, so the whole quantity is committed at once and not room by room. Who does what, and in what order, is the guide on who supplies stone tops for hotels.
The second effect is phased handover: floors released at different times call for more templates and more deliveries, each phase a queue of its own. The third is storage, because when installation slips the finished pieces already exist and have to stand somewhere decent: the guide on storing stone on site. Here time is the heaviest item of all, because an opening date that moves costs more than any detail of the supply.
The lines to put in the order
Six items that cost nothing while negotiating:
- the installation date tied to the template and not to the signing, with the working days between the two;
- who commits the slab, from when, and what happens if it is sold meanwhile;
- what has to be ready on template day, written as a condition and not a hope;
- what a change of appliance or size after the template costs in time;
- who answers for the pieces between delivery and installation, and where they stand;
- whether attic stock is planned, and which slab it comes from.
How we work
We work natural stone in our own workshop, from marble to onyx, and we follow a project from the drawing to the installation: the queue this page describes is ours from end to end, and we give a date when we know which slab the piece comes out of and when the template can be taken, not before. We do not use resin to stiffen our slabs: wide surfaces need a support, and the mesh on the back is in itself a good one. For backlit onyx we use dimmable warm-light LEDs, because the light must not heat the stone.
The work we do is in the collections, project supply in the contract section, and the contacts lead to the people who follow the job.
Frequently asked questions
Why will nobody give me a date at the quotation stage?
Because the two pieces of information that settle it are missing: which slab, and when the template can be taken. A date given then estimates the average case, and the average case does not exist. The useful question is «how many days pass between template and installation, and on what do they depend».
Can the top be cut from drawings, without a template?
For a piece that stands free, such as a table top, yes. For one that meets walls and units, no: design measurements and real ones hardly ever coincide, and a piece cut from the drawing arrives right in size and wrong against the wall.
How much time does changing the sink after the template cost?
It depends where in the queue you are. Before cutting, the shop drawing is redone; after cutting, the piece is remade, with the added problem of finding that slab again. It is why the appliances' sheets are asked for before the template.
Should the stone be ordered before or after the units?
The stone is chosen and committed first; the units are installed before the template. The common mistake is to treat stone as the last item on the list, when it is the first that needs time.
Ask for a quotation The tables collection
This page describes good practice in organising a supply of natural stone and does not replace a works programme. It quotes no prices, no delivery times, no tolerance values and no company cases, and it cites no technical standards: how long a supply takes depends on the material, the sizes, the site and the order, and is to be agreed between the parties.