The stone has arrived on site and fitting is delayed: where is it kept?
In short. A finished slab that reaches site and is not fitted straight away goes through the most fragile stage of the whole supply: it is complete, it is heavy, and it is standing somewhere nobody designed for it. It is kept upright rather than flat, on a support that holds it along its whole length, under cover, away from site water and from the materials that stain. The place is settled before delivery, not when the lorry is at the gate. And who answers for damage depends on where the stone stood and on what was written down when it was handed over.
Why a slab cannot be set down like a crate
Stone takes a load that crushes it very well and a load that bends it very badly. A long worktop resting on two timbers set far apart is not supported: it is a beam loaded by its own weight, and it holds until somebody puts a bag on it. When it goes, it does not go at the weakest point of the stone but at the weakest point of the support, and that point is almost always a cut-out: the sink, the hob, a narrow section of the layout. Why cut-outs are the critical points we set out in the guide on cracks at the sink and hob cut-outs.
The second reason is that a finished piece is finished: calibrated, polished or brushed, with the edges worked and the holes made. A scratch on a polished edge is not taken back on site the way it is taken back in the workshop, and a chip is repaired but stays a repair. What a piece of this kind weighs, and what has to carry it, is in the guide on the weight of a stone top.
Upright or flat?
Upright, always, unless there is a continuous surface to lay it on. A vertical slab, resting on its long edge and leaning slightly against an A-frame, works in compression and sits quietly for weeks; the same slab laid flat on two bearers works in bending from the first minute. The rules that are habit in a workshop and unknown on site are few:
- the load goes on the long edge and not on a corner: a corner carrying the whole weight chips on its own, with nobody touching it;
- a timber or a felt belongs between stone and floor: a slab set onto the screed draws up the moisture of the floor;
- the lean is slight and even, and the support reaches high: a slab held only at the bottom levers out and opens;
- a soft spacer goes between two pieces set together, and two finished faces are not rested against each other with nothing in between;
- small pieces — upstands, skirtings, returns — are kept apart: they are the ones that break most and that nobody counts.
What does the place have to offer?
The place is not a logistical detail: it is half the problem. What is needed is a spot under cover, dry, on a level floor that can carry the weight, out of the way of plant. Two conditions matter more than the rest. The first is that the place is of no use to anybody else: stone put where a scaffold has to pass in three days will be moved, and every move is one more risk, because damage in storage is nearly always damage in handling. The second is that it is away from what stains: plaster and mortar being worked, steel being cut or welded, resins, site cleaning products.
On natural stone these neighbours are not harmless, because the surface absorbs. Site water standing on a pale marble leaves a mark that does not go away by drying it; wet steel filings leave a rust stain that goes in; damp cardboard rested on a polished slab transfers the colour of the cardboard. What comes out and what stays is in the guide on marble stains and etching; telling damage from a character of the stone is in the one on defect or natural feature.
Time on its own is not the problem: stone does not age in a store. What grows with time is exposure to the site, and the condition time makes relevant is frost in a building that is not yet heated: a slab saturated with water and then frozen is stressed from inside, which is why dry storage counts for more than warm storage. Frost on stone is described in the guide on a marble table outdoors, and the long storage of a hotel's reserve stone has rules of its own.
Packing, lastly, is for the journey and not for the month that follows: an adhesive film left in the sun bakes and leaves its adhesive on a finished surface, whereas a rigid protection board, rested and not stuck on, takes the knocks instead of the edge and can stay until fitting.
Who answers for damage in storage?
It is not a question to be answered in general, and that is exactly why it is worth closing beforehand. In practice the answer turns on two things, both of which can be written down in advance: whose custody the piece was in at the moment of the damage, and what was put in writing when the stone was delivered. The recurring situations are three, and they belong in the order rather than on site:
- the stone stays in the workshop until the place is ready and is delivered for fitting: the simplest, because there is no period of custody to regulate;
- the stone is delivered and fitted later by whoever supplied it: here it has to be said who holds it in the meantime, and where;
- the stone is delivered and fitted by somebody else: this is where disputes arise most often, because between delivery and fitting the piece is in the hands of someone who did not make it.
Whichever the case, the document that counts is the delivery one. A piece accepted at delivery is a piece that has been looked at: that is why pieces are looked at one by one before anything is signed, and visible damage is noted there and then, with a photograph. Who carries them up and who fits them is a division of duties to be settled the same way, and it is in the guide on who carries the stone top up; unloading day then needs what template day needs, plus the storage place already empty and set up.
How we work
We work natural stone in our own workshop, from marble to onyx, and we follow a project from drawing to fitting: the stage this page is about is the one moment when the piece is finished and belongs neither to us nor to the wall. We do not use resin to stiffen slabs: wide surfaces need a support, and the mesh on the back is in itself a good one. On backlit onyx we use dimmable warm-light LEDs, because the light must not heat the stone.
A supply that stands still until the place is ready is the simplest route of all, and it is agreed beforehand. The work we do is in the collections, project supply in the contract section, and the contacts lead to the people who follow the job.
Can a slab be left flat on the floor for a few days?
Only if there is a continuous surface beneath it supporting its whole area, with something between stone and floor. Flat on two or three bearers, no: that is the position in which a worktop with its cut-outs already made cracks without anybody knocking it.
Is the adhesive film left on until fitting?
No — not in the sun and not for weeks: the adhesive bakes and leaves residue on a finished surface. The protection that stays is the rigid, rested kind; adhesives come off as soon as the piece is under cover.
If a piece breaks on site before fitting, who pays?
It depends on who had custody and on what was written at delivery, and it is not something to settle once the damage has happened. The two lines to put in the order are: who holds the pieces between delivery and fitting, and in what place.
How much space is needed to keep the pieces on site?
Less than expected on plan and more than expected in manoeuvre: the pieces stand upright and take up little, but they have to be slid in and taken out again without dragging them. The useful measurement to ask for is not the area, it is the clear width from the unloading point to the point of fitting.
Ask for a quotation The tables collection
This page describes good practice for storing and handling finished pieces of natural stone and does not replace a design. It quotes no prices, no response times, no tolerance values and no company case histories, and it cites no technical standards: custody of materials on site and the allocation of risk depend on the order and the specification, and have to be agreed between the parties. The guidance on support, protection and delivery has to be verified case by case, because it depends on the stone, the sizes and the site.